NYC kitchen remodel permits 2026: board approvals, Alt‑1 vs Alt‑2, real timelines
- Richard Golding
- Jan 9
- 2 min read

Full NYC kitchen remodel ranges $60,000–$180,000+ depending on finishes, scope, and size.
Most projects with wiring, plumbing, layout changes require a DOB permit (Alt2) filed through DOB NOW: Build.
Board approvals (co‑op/condo) and freight elevator delivery windows can add time and cost.
Typical timeline: 8–16 weeks including permits and construction.
Internal links: Metro Contractors NYC booking & gallery.
Why Remodel Now in January 2026
Winter offers easier scheduling with designers and contractors before spring demand spikes. In NYC, permit filings through DOB NOW: Build streamline reviews, but scheduling can still take 4–6 weeks due to review queues.
Costs & Budget Breakdown (NYC)

Typical Ranges
Cabinetry & Millwork: $18,000–$60,000
Countertops (stone): $6,000–$20,000
Appliances: $8,000–$30,000
Plumbing & Electrical: $10,000–$30,000
Flooring: $3,000–$12,000
Design Fees: $2,000–$8,000
Assumptions: NYC 80–200 sq ft kitchen, Manhattan/Brooklyn Heights/UES delivery windows, union vs non‑union labor rates. Custom cabinetry and stone at high end.
Why Costs Vary
Layout Changes: Adding beams or moving walls increases structural work, permit filings, and time.
High‑end Finishes: Custom cabinetry + imported stone drives costs.
Site Logistic Fees: Freight elevator reservations and curb permits.
NYC DOB Permits — What You Need to Know
Do You Need a Permit?
Most full kitchen remodels involving plumbing, gas, electrical or layout require a permit. Minor cabinet swaps do not trigger DOB filing requirements.
Permit Types & Filing

Kitchens with multiple trades and layout changes often fall under an Alteration Type 2 (Alt2) permit, filed electronically via DOB NOW: Build.
Dob Now: Build is the City’s online portal for filing plans and tracking approvals.
A licensed architect or engineer typically must prepare and file plans.
Board & Building Constraints
For co‑ops/condos (Park Slope, Astoria, Harlem), board approvals are separate from DOB permits and can take additional 2–6 weeks.
Process & Timeline
Design & Budgeting: 1–3 weeks
Permits & DOB NOW Filing: 4–6+ weeks
Demolition & Rough‑in: 2–3 weeks
Finishes & Inspections: 3–5 weeks Total: 8–16+ weeks from kickoff.
Site Logistics (Elevators & Hours)
Work times and elevator reservations must align with building management rules, especially in walk‑ups and high‑rise elevator buildings.
Metro Contractors LLC Expertise
Metro helps NYC homeowners plan and file permits, handle DOB NOW submissions, and manage inspections. Our teams work in Harlem, SoHo, UES, and Brooklyn Heights.
Internal Links
See recent projects: https://www.metrocontractors.nyc/gallery Ready to book? https://www.metrocontractors.nyc/book-online
External Links
FAQs
Do I need a permit for new cabinets in NYC?
No if only cabinets are swapped in without plumbing or structural changes.
How long does DOB review take?
Plan exam typically 4–6 weeks but can vary with scope.
Can Metro file permits for me?
Yes, Metro’s team prepares and files DOB applications.
Does a permit affect board approvals?
Yes, you must get board ok before DOB permits for co‑ops.
Are deliveries allowed on weekends?
Check building rules; many restrict weekend freight use.
Talk with Metro to get a custom cost estimate and permit plan today.