NYC Kitchen Remodel Timeline 2026: Co-op Approvals, DOB Steps, Holiday Scheduling
- Richard Golding
- Nov 20
- 3 min read

Why NYC Kitchen Timelines Look Different Than Anywhere Else
NYC kitchens sit inside dense multi-family structures with strict building rules, limited work hours, and multiple layers of approval before a contractor can touch a wall. Unlike single-family homes, renovations in NYC must pass through:
Board alteration agreements
Management company approvals
DOB filing review
Trade-permit releases
Superintendent sign-offs
Freight elevator scheduling
And during November–January, timelines stretch further due to holiday blackouts, building super vacations, and shortened city inspection availability.
Phase 1 — Design + Budgeting (1–3 weeks)
Work begins with:
On-site walkthrough
Measurements in a prewar or postwar layout
Cabinet design and appliance spec selection
Preliminary electrical and plumbing review
Initial budgeting
NYC complexity: Prewar trade conditions (Harlem, Park Slope, UWS) often hide risers behind plaster, so your GC will account for potential reroutes in the planning stage.
Most issues are discovered here that determine how long an Alt-2 filing will take.
Phase 2 — Co-op or Condo Approval (2–8 weeks)
Co-op approvals are the #1 timeline driver in NYC.
What you must submit:
Architectural drawings
Appliance spec sheets
Plumbing/electrical details
Contractor insurance forms
Contractor license
Neighbor notification (in some buildings)
Common delays:
Monthly board meetings (many boards only meet once per month)
Holiday shutdowns (Thanksgiving → early January)
Building architect review cycles
Neighborhood examples:
UWS + Harlem co-ops: Strict noise rules and older risers → longer design review
SoHo lofts: Fewer restrictions but more structural coordination
Brooklyn Heights co-ops: Often require additional acoustic details
If you start a kitchen submission after November 15, many buildings will not issue approval before the New Year.
Phase 3 — DOB Alt-2 Filing (3–8 weeks)
A NYC kitchen remodel that touches plumbing, electrical, or walls almost always requires an Alt-2 filing.
Your architect/engineer will:
Prepare DOB drawings
Upload forms through DOB NOW: Build
Respond to examiner objections
Coordinate trade permits for plumbing and electrical
Timeline expectations:
Simple layouts: 3–4 weeks
Prewar upgrades: 4–6 weeks
Complex venting/move of gas appliances: 6–8 weeks
Gas-appliance relocations trigger additional scrutiny, especially in buildings with shared risers.
Phase 4 — Pre-Construction Logistics (1–2 weeks)
NYC buildings require extensive prep:
Building superintendent coordination
Freight elevator reservations
Protection routes
Work hours (often 9–4 pm)
Water + gas shut-down windows
Material staging
Everything must fit in the elevator or be hoisted through windows. Appliance delivery must be timed to elevator availability.
Phase 5 — Construction (4–8 weeks)
Typical NYC kitchen remodel sequence:
Demolition (1 week)
Masonite protection
Debris removal via freight elevator
Rough plumbing + electrical (1–2 weeks)
DOB inspections (rough-in) (1 week)
Close-up framing + leveling (1 week)
Cabinet install (1 week)
Countertop templates & slab fabrication (1–2 weeks)
Finish plumbing + electrical (1 week)
Final inspections + punchlist (1 week)
Prewar buildings in Harlem, Park Slope, and UWS with uneven floors may need extra leveling days.
Phase 6 — DOB + Building Close-Out (1–2 weeks)
Once the work is completed:
Electrician schedules DOB inspection
Plumber schedules DOB inspection
Final sign-offs issued
Board may require superintendent walkthrough
Deposit refund processed
Important: If inspections fall between Thanksgiving and January 3, availability is extremely limited, often adding 1–2 weeks automatically.

How Holiday Scheduling Affects NYC Kitchen Timelines
NYC has strict building and management schedules:
Late November → New Year:
Many boards do not meet
Contractors run shorter crews
DOB inspectors book out faster
Freight elevators get restricted
Supers take holiday time off
This means a kitchen that should be 12 weeks can easily stretch to 16–20 weeks.
Pro Tip:
If your goal is a spring 2026 remodel, submit your co-op packet no later than January 15.
Typical Full Timeline Overview
Phase | Duration |
Design & budgeting | 1–3 weeks |
Co-op/condo approval | 2–8 weeks |
DOB Alt-2 filing | 3–8 weeks |
Pre-construction logistics | 1–2 weeks |
Construction | 4–8 weeks |
Inspections & close-out | 1–2 weeks |
Total (Average) | 12–20 weeks |
How to Choose a Contractor for NYC Kitchen Timelines
Hire a GC with deep NYC experience:
Knows board & management cycles
Prepares DOB filings quickly
Plans around holiday blackout dates
Has existing relationships with supers
Understands freight elevator logistics
Metro Contractors LLC specializes in prewar and co-op renovations throughout NYC.
Book a consultation:
View project gallery:
External Links
FAQ
How long does a full NYC kitchen remodel take? Most kitchens take 12–20 weeks from design to close-out.
Why do co-ops slow down the process? Board cycles, building architect reviews, and holiday blackouts.
Do I always need an Alt-2 permit? Yes if you move plumbing, electrical, or partitions.