NYC Co-Op vs Rent-Stabilized Renovations: Permit Traps in Kitchen & Bath Projects 2025
- Richard Golding
- 4 days ago
- 2 min read

Introduction
New York City homeowners and tenants often assume that kitchen or bath upgrades follow the same rules across all apartments. In reality, they don’t. A co-op in Park Slope or SoHo might only approve renovations once a managing agent signs off on insurance and DOB filings, while a rent-stabilized unit in Harlem or Astoria can’t even change fixtures without HPD review.
By understanding which filings apply — Alt-1 vs Alt-2, licensed trade work, or simple cosmetic refreshes — you avoid project shutdowns and wasted fees.
Section 1: What’s the difference between Co-Op and Rent-Stabilized approvals?
A co-op board controls not only the aesthetics but also the liability. Renovating without a signed alteration agreement can violate the proprietary lease. Rent-stabilized units, by contrast, fall under state rent laws and HPD oversight, where permanent improvements affect legal rent calculations.
Co-Op Key Steps
File Alt-2 (non-structural) with DOB via DOB NOW.
Obtain building management’s alteration agreement.
Show proof of licensed electrician/plumber.
Supply $1M liability insurance certificate naming the co-op.
Typical cost: $3 k – $5 k in administrative fees and 6–8 weeks approval.
Rent-Stabilized Key Steps
HPD requires work description to ensure it doesn’t displace tenants.
DOB filing may upgrade to Alt-1 if layout changes.
Owner must register new rent post-renovation (RPIE form).
Typical cost: $2 k – $4 k filings + $500–$800 HPD compliance consultant.
Section 2: The top 5 permit traps contractors face
1. Wrong filing type (Alt-2 vs Alt-1)Changing plumbing fixtures across rooms? That’s Alt-1 territory — even if walls stay.
2. Missing co-op insurance riders Board packets often require specific “Waiver of Subrogation” language.
3. Work-hour and freight elevator limits UWS and Park Slope buildings often restrict hours 9 a.m.– 4 p.m.
4. Outdated HPD registrations HPD refuses permit issuance if the owner registration isn’t current.
5. Unlicensed trades DOB can halt a job if plumbers/electricians aren’t active in the License Board database.
Section 3: Typical costs and timelines (2025)
Building Type | Avg Permit Fee + Admin | Approval Time | Common Delay Factor |
Co-Op (Alt-2) | $3,500 – $5,500 | 6 – 8 weeks | Board signatures and insurance |
Condo | $2,500 – $4,000 | 4 – 6 weeks | DOB plan review |
Rent-Stabilized (Alt-1) | $4,000 – $6,000 | 8 – 10 weeks | HPD approval lag |
FAQ
Do co-op boards need a DOB permit to approve my remodel? Yes. Most boards require proof of a filed Alt-2 or Letter of Completion before granting access.
Can a tenant in a rent-stabilized unit remodel a bathroom? Only the landlord can apply for permits; tenant work without HPD sign-off risks penalties.
How long does DOB approval take in late 2025? 20–30 days average for Alt-2 filings under DOB NOW: Build.
Is union labor mandatory? Not by DOB, but many Manhattan co-ops require union subs for liability.
Author Bio & Expertise