NYC Bathroom Remodel Permits & Timeline 2025
- Richard Golding
- Oct 13
- 3 min read

Most NYC bathroom remodels file as ALT2 with separate LAA plumbing permits, plus electrical permits. Co‑ops and condos require a building alteration agreement and proof of insurance. Realistic timelines run 10–16 weeks from board packet to DOB sign‑off on a standard bath. Start now to avoid holiday and inspector bottlenecks. Book a site visit and we will confirm scope, filings, and elevator rules. New York City Government+2New York City Government+2
What “permit” actually means here
NYC has four construction-application types: NB, ALT1, ALT2, ALT3. ALT2 covers most kitchen and bathroom renovations that do not change use, egress, or occupancy. Plumbing work also needs a Licensed Master Plumber to file a Limited Alteration Application (LAA) in DOB NOW: Build. Electrical work files separately. New York City Government+2New York City Government+2
Typical filing stack for a bathroom
ALT2 plans by a PE or RA
LAA for plumbing fixture changes, relocations, or riser work
Electrical permit for new circuits, GFCI, or lighting
Asbestos investigation where required by scope and building policy
If your building asks, acoustic and waterproofing specs with test data
Plumbing permits are issued only to an LMP, who schedules pressure tests and inspections with DOB. New York City Government
Co‑op and condo approvals most blogs skip
Boards enforce alteration agreements that define work hours, insurance, sound, waterproofing, and waste routes. The agreement often requires stamped drawings, neighbors’ notices, and refundable deposits. Getting board sign‑off can take 2–6 weeks depending on meeting cadence. We package all documents to fit your building’s checklist. CooperBuild
Freight elevators, work hours, and prewar realities
In Harlem, Park Slope, and the Upper West Side, many buildings limit construction to 9–4 weekdays and require freight reservations. Prewar stacks are tight, so fixture relocation may trigger more LAA scope and riser coordination with the super. Planning these logistics early protects the schedule.
The 2025 schedule that actually holds
Below is a conservative plan for a standard 5×8 to 6×9 bath with a new tub‑to‑shower conversion, tile throughout, and updated lighting.
Weeks 1–2: Pre‑design and board packet
Measure, select finish targets, outline waterproofing, and draft board packet.
Weeks 3–4: Board review
Answer questions, issue revisions, provide insurance and license copies.
Weeks 5–8: DOB filings
Submit ALT2. LMP files LAA. If self‑certifiable, approvals can be faster; otherwise allow examiner cycles. Electrical permit prepped in parallel. New York City Government+1
Weeks 9–10: Procurement and elevator scheduling
Order long‑lead items: valves, shower glass, stone tops, specialty tile.
Weeks 11–14: Construction
Demo and protection
Rough plumbing and electrical
DOB plumbing inspection
Close walls, waterproof, tile, set fixtures
Paint, trim, punch
Weeks 15–16: Final inspections and sign‑off
Plumbing and electrical closeouts. ALT2 sign‑off.
DOB continues to post fall enforcement and schedule notes on its Service Updates page; we use that feed to avoid inspection surprises. New York City Government
Permit path: ALT2 vs LAA in plain English
ALT2 = the building permit tied to your plans. The PE/RA files through DOB NOW: Build. Most bathroom remodels use ALT2. New York City Government
LAA = the plumber’s permit for limited plumbing scope. It rides alongside ALT2 and is issued only to an LMP, who also schedules required tests and inspections. New York City Government+1
What affects the timeline most
Board cadence and holiday blackouts
Elevator access and building work hours
Inspection availability during fall peaks
Long‑lead materials like custom shower glass

Cost ranges you can actually budget
These ranges assume a 5×8 to 6×9 bath, with quality tile and mid‑range fixtures. They exclude luxury stone slabs and full riser replacements.
Code‑clean refresh (same locations): $28k–$45k
Mid‑range with tub‑to‑shower + lighting: $45k–$75k
High finish level or layout changes: $75k–$120k+
Recent NYC guides and homeowner reports cluster in these bands for 2025; we tailor scope to the building and unit. NYC Renovation Guide+1
Waterproofing, sound, and why the board cares
We specify a continuous waterproofing membrane with flood test where required, sound‑attenuating underlayment, and cove/band details at wall‑floor junctures. These details reduce neighbor complaints and speed board sign‑off because they match modern alteration‑agreement language.
Inspections you should expect
Plumbing: rough and final
Electrical: rough and final if circuits change
Special inspections only if triggered by scope
The LMP arranges plumbing tests and attends DOB inspections. New York City Government
Neighborhood notes
Harlem & UWS: freight elevator reservations and limited work windows are common.
Park Slope: walk‑ups mean extra protection and carry costs for stair carries.
Astoria & LIC: newer condos often require pre‑approved contractor lists.
Common pitfalls and how we prevent them
Missing alteration agreement pages → We preflight your packet against the building’s template.
Tile lead times → We lock selections before filing to protect schedule.
Unclear plumbing scope → Our LMP confirms whether LAA is enough or if full plan review is needed. New York City Government